
| Length (Feet): | 125' |
|---|---|
| Width: | 4 ft. |
| Thickness: | 3/8" |
| Application: | Heating Radiant Heat |
| R-Value: | 3.8 |
| Material: | Aluminum Polyethylene |
This method is fine as long as the structure can support the weight of the new slab. Thicker insulation in the below-floor joists may do a better job of limiting downward heat loss than this foil, however.
this will work, but why all the weight of motar? is it going to be all tile? If not consider using the track system, you will not need the barrier as it is built into the tracks and is only a half inch thick total.
Not sure how sturdy of a floor your looking for, or how much area your talking about, but the 1 1/2" mortar mix sounds like a lot of work, and a huge mess if it doesn't set up right. aluminum panels are available that attach to the underside of your floors that hold your tubing, and spreads the heat throughout aluminum. But of coarse the undersides of your floor would need to be exposed to apply. So I would use hydronic where floor undersides are exposed and the electric underfloor heating mesh when working above the subfloor. Sent from Samsung mobile
Yes, you are correct. I would recommend using a metal mesh in the concrete (placed below the pex but above the insulation) and using something like Schluter Ditra to isolate your tile from the 2" heated slab. I had some travertine (a soft material) crack when I heated up the floor and caused it to expand. The Ditra should provide enough isolation to prevent that from happening. Also, I would space the pex tubing about 6-8 inches apart instead of the 12 inches that's often recommended, as I can feel a cold temperature in between the 12 inch runs. Pex Supply sells a tubing spacer that might be useful (it's a gray plastic u-channel with u-shaped openings in the sidewalls). Finally, be sure to run the pex through a 90 degree conduit where it enters the concrete so you don't get a crimp at that point (assuming a 90 degree bend there, as is common).
That will work, but you need two inches of concrete with Fibermesh or similar in the mix over the pipes to avoid cracks. That is a total of eight inches of concrete which is probably way more than you need. Another approach is to lay the foil barrier on top of compacted gravel or a thin layer of sand. Then lay down 6x6 welded wire mesh over the barrier foil. Use flat pieces as the rolls are next to impossible to get laid flat. Use plastic zip ties to attach the Pex to the mesh. One nice thing about the mesh is it gives you a grid for easy spacing of the loops. Pressurize the Pex and leave a gauge on it overnight to confirm no leaks before you pour. Leave the pressure on for the pour. If the pipe gets cut with a shovel or something it will be very obvious and easy to fix before the mud sets. Put little Dobbies or chairs under the mesh before you pour to lift the pipes up to the mid point of the slab. Depending on your loads you may only need four inches of concrete. Check with an engineer or someone with experience to confirm. A residential floor with good compacted sub grade can be four inches. If it is a garage with heavy point loads from commercial trucks, jacks or equipment like lathes or presses then six inches is a more appropriate thickness. If you are putting load bearing walls on the slab then you need an engineer to look at it. In that case a four inch slab with grade beams under the loads is more likely to be the proper approach. The main difference between you proposed topping slab and using the structural slab for heat is the thermal mass. A two inch thick topping slab with a thermal break below it will change temperature a lot faster than a four or six inch thick slab. If you want steady temp 24/7 then a thick slab is ideal. If you want faster response and have a cold room warm up quicker go with the two inch topping slab. But quick is only relative to a thick slab. It will still take a couple or three hours for a two inch slab to get up to temp from a cold start. Choose an appropriate thermostat that can handle the large thermal mass and anticipate. Otherwise you can massively overshoot and have a room that is too hot and hard to cool down. This is also the reason that controlling the circulating water temp based on outdoor air temp is a good idea with a high thermal mass radiant system. Good luck. A warm floor is a wonderful way to heat I'd you do it right. Sent from my iPhone
I don't know if 6" is code in your area but that's excessive. Lay down your foil with 16" to 24" of dirt on top of the foil. Then do a 4" concrete pad.. It should look: 4. 4" concrete 3. 16" to 24" of dirt 2. Foil 1. Mother earth. GM/iPhone
The fact that you have an existing slab makes insulation less of a necessity. The existing slab will hold much of the heat. We still recommend putting some kind of barrier down.
It is always a good idea to insulate below the tubing throughout the slab. Heat can be lost not only through the perimeter of the house, but also straight down.
In my opinion no other insulation is required, however you really need to check with your local building department to see what the local code requirements are.
Yes, it can.
There is no reason you couldn't use Concrete Barrier Foil as you described, however you need to check with your local building department to see if this meets local code requirements.
You would need to have a minimum of 3/4" of concrete over the PEX.
Yes, but the R-value of the foil will decrease.
Adding more insulation would not hurt your system.
That procedure should work just fine.